Maerdy Windfarm

     Home    Help    Contact    Cymraeg

Maerdy Windfarm
Proposal

 


The Windfarm


The windfarm site is located to the north of Maerdy and Treorchy (See figure 1).

Figure 1: Windfarm Location


 

The windfarm is sited on a plateau of upland grazing land (See Figure 2). To the north of the site is the Lluest-wen reservoir; to the south Treorchy; to the east the disused Maerdy Colliery Site and coal tip; and to the west the Tynewydd Forest.


Figure 2: Windfarm Layout

There would be eight wind turbines, each with a tower height of 80 m and three 44 m blades, painted white, together with the hub giving a total height to the tip of the turbine blade of 125 m. Each wind turbine is 3 MW installed capacity producing electricity equivalent to the annual consumption of 1 700 UK households. The eight turbines would supply total electricity equivalent to the consumption of 13 600 homes each year.

Electricity from each turbine is carried back to a windfarm substation by underground cables. The windfarm substation is sited on lower ground in the north-west of the site adjacent to forestry and consists of a 20 m x 10 m single storey building clad in local stone, with external electrical equipment and a belt of new tree planting around it. Other equipment includes an 80 m anemometer mast to measure the wind, 2.5 m wide at the base and 40 cm at the top.

The windfarm substation would be connected to the Maerdy Town substation 1.5 km to the southwest of the windfarm. The connection will be undertaken and owned by the operator of the local electricity network; Western Power Distribution (WPD), and is not part of the windfarm planning application. Connection would either be overhead wooden pole line similar to that surrounding the site or underground line. The route has not been decided, but would likely be either adjacent to an existing overhead line or adjacent to the reservoir road from Maerdy colliery site, before branching west to the windfarm (See Figure 2).

Construction will last 9-12 months and will involve temporary stone crane pads adjacent to each turbine and a temporary construction compound located adjacent to the forestry. Stone access tracks connect the wind turbines and substation enabling the construction; these are reduced in size, but left in-situ, following construction to allow access for maintenance.

Access to the windfarm is from near the top of the A4061 Hirwaun-Treherbert road, along an existing forestry track. All substantial traffic will be from the north with potential quarries to the north and turbines delivered on the A465 from Swansea (See Figure 3).

Figure 3: Access

The windfarm would operate for 25 years after which it would be decommissioned. Decommissioning takes 3 - 6 months and involves removal of all turbines and other surface infrastructure to ground level. Underground foundations (2 m deep) and cables are left in-situ and landscaped over, as it would be more disturbing to remove them. The grid connection would be removed unless it was needed for some other part of the electricity network by then. The access tracks would all be covered over and revegetated, save any the local authority permitted to be retained for farming use.

An independent bank bond will be provided to the local authority so that they have the security to remove the windfarm to their own satisfaction if the windfarm operator did not honour their obligations. Any windfarm on the site beyond 25 years would be the subject of planning policy and permission at the time.