This report has
been prepared to outline proposals for community funds associated
with the Maerdy Windfarm. The report covers the reasoning for a community
fund, policy and guidance on funds and consultation conducted by the
Developer on possible routes for a fund.
This report is
intended to facilitate discussion with interested parties and provide
a basis for proposals to be agreed should the windfarm be granted
planning permission. Interested parties may include: Rhondda Cynon
Taff County Borough Council (RCT), Community Groups, AM’s, etc.
It is intended
that a community fund, deliverable by the Windfarm Developer, is secured
by RCT through either legal measure or planning condition as appropriate,
to provide confidence on their delivery.
The Maerdy Windfarm
will deliver financial benefit if it goes ahead to the following organisations:
- The Windfarm
Developer
- The Local
Landowner
- The Forestry
Commission
- RCT Council
The local community
may vicariously benefit through the substantial rates that RCT will
collect from the windfarm. However, The Developer wishes to ensure
that the local community also receive direct financial benefit as
a stakeholder in the windfarm.
National Planning
Policy makes clear, and the Developer endorses, that the availability
of a community fund should not influence a planning decision, such
that a windfarm that would have been turned down on environmental
or other grounds is given the go ahead.
Technical Advice
Note 8: Planning for Renewable Energy (TAN8) provides the most up
to date and relevant guidance with regard to windfarms and community
benefit schemes:
.
|
2.15
Developers, in consultation with local planning authorities,
should take an active role in engaging with the local community
on renewable energy proposals. This should include pre-application
discussion and provision of background information on the renewable
energy technology that is proposed.
2.16
Experience has shown that there are opportunities to achieve
community benefits through major wind farm development. Some
benefits can be justified as mitigation of development impacts
through the planning process. In addition, developers may offer
benefits not directly related to the planning process. Annex
B provides further information and examples about the types
of community benefit which have been provided. Local planning
authorities, where reasonably practical, should facilitate and
encourage such proposals. The Welsh Development Agency, and
others can support and advise on community involvement in developing
renewable energy and benefiting from it. Local planning authorities
should make clear in their development plans the scope of possible
“planning contributions”. However, such contributions
should not enable permission to be given to a proposal that
otherwise would be unacceptable in planning terms.
Annex
B
Community Benefits Arising out of the Development of Wind Farms
in Wales
Developer
offers
1.3
The developer might wish to volunteer “gains” outside
obligations that could be legitimately described as necessary
for the development to proceed. Such “gains” could
be offered as part of the planning process, as outlined below,
or they could be undertaken as a separate exercise. The courts
have held that this approach is not, in itself, unlawful. Whether
the developer enters into an agreement with the local planning
authority or offers these extra benefits unilaterally (as he
is permitted to do under section 106), the important point here
is that, as such offers are not necessary for the development
to proceed, they must not impact upon the decision-making process.
2.
Community Benefits – outside of the planning process
2.1
It is perfectly acceptable for a business to enter into a legally
binding agreement with third parties to deliver particular and
agreed benefits to the community. Many local planning authorities
would be more comfortable with this approach as it separates,
more clearly, community benefits from the planning decision.
It is important that the developer is able to identify suitable
local representative people or organisations with whom it can
negotiate. If there are funds to be administered then an appropriately
constituted and regulated body must be identified or created.
2.2
Such benefits offered to local communities could take the form
of one or more of:-
• in-kind benefits such as the construction of a needed
community facility.
• a lump sum financial payment for the benefit of the
community.
• annual payments to the community.
• a commitment from the developer to use local labour
and/or contractors/services wherever possible.
2.3
It is, however, considered to be essential that:-
• benefits are negotiated with appropriate and representative
persons or bodies.
• benefits are channelled through a regulated and properly
constituted body or trust (this could include the local authority).
• benefits are utilised for an agreed range of appropriate
uses that would all fall within the definition of sustainable
development.
• at least part of any annual payment benefits should
be invested in carbon emissions reduction measures in the local
community.
2.4
It must be clear that the provision of benefits is on a purely
voluntary basis with no connection to the planning application
process |
There is no relevant
policy within the Rhondda Local Plan, however, the Cynon Valley Local
Plan does state that the Council will seek provision of environmental
and community benefits from Developers.
An extensive public
consultation was conducted on preliminary proposals for the windfarm
during December 2005 and January 2006. The public consultation covered
a wide range of areas inviting people to comment on the proposals.
The consultation also, specifically requested comments on community
benefits; see extract from consultation questions below
Q5.
How best do you think community funding from the project should
flow?· to community projects· to individuals through
shares in the windfarm· through discounts on electricity
prices
Q6. Have
you any specific ideas on applying community funding? |
Responses
27 people made written comments in response to the consultation, 9
of these made specific comments regarding community funding. A report
was prepared for RCT on the public consultation that included all
responses in full: Maerdy Windfarm Project: Report on Public Consultation
on Preliminary Proposals 20/02/06 (included within planning documents
as ES appendix). The responses regarding community funding are summarised
in the Table 2.1 below:
Table 2.1: Responses
to Public Consultation Regarding Community Benefit
1
Balance funding between the most disadvantaged and needy and as
many people as possible; Community groups, subsidising core services;
Benefits identified as consequence of windfarm and highly visible
and credible
2 Resources for young people – networked centres, internet
cafes, somewhere to play pool
3 Discounts in electricity prices
4 Reduction in energy costs, not community projects; Direct grant
funding for household wind turbines / solar panels
5 Fund community projects
6 Benefits are illusionary, dwarfed by disadvantages
7 Tourist development, but windfarms are not a tourist attraction
8 Yes to community projects; No to individual shares in windfarm;
No to discounts on electricity prices; Funding to Maerdy Community
Centre
9 Mountain bike path, and footpath; Natural woodland planted |
Meetings have
been held with Maerdy Communities First and RCT Council. No specific
issues came out of the meetings.
The key questions
to be decided by any community fund scheme are:
- How much funding
?
- Where is the
funding applied ?
- To what is
the funding applied ?
- How is the
funding applied ?
The level of funding
available depends on the financial viability of the windfarm in question
and what is equitable.
Windfarm viability
is dependent on the size of the windfarm, the wind speed and the electricity
sale price available. Windfarm economics are highly sensitive to all
of these factors. Economies of scale are significant; revenues rise
at an exponential rate to windspeed and electricity sales prices are
very un-reliable as they are exposed to large political and economic
risk.
Maerdy Windfarm
is 24MW installed capacity, there are bigger projects in more remote
locations and also smaller projects. Windspeed is average; there are
more exposed windier sites and also less windy lowland sites.
The electricity
price that Maerdy can secure is dependent on how quickly it can secure
planning permission and be constructed. The UK Government Energy Review
2006 announced proposals to band the support mechanism for renewable
energy. If progressed this would reduce the economic support that
onshore windfarms receive in the future, with projects commissioned
after 2009/10 receiving lower funding. Maerdy would still proceed
if built after this date, but its electricity sale price would be
lower and hence the economics worse and the fund available to all
stakeholders reduced.
The developer
has evaluated the project economics and proposes a total fund of £50,000
per year, indexed at 1.5%. Windfarm revenues are variable from year
to year, however fixed funding options are deemed more appropriate
to the local community enabling planning with confidence. The need
for clarity and certainty in funding came through as a comment in
public meetings held during consultation.
The fund is indexed
at 1.5% so that it inflates. 1.5% is the average of UK and EU inflation
targets. The windfarm is likely to experience declining sale prices
over the course of its life.
This fund equates
to just over £2,083 per MW of installed generating capacity.
As comparisons the fund established for the local recently commissioned
Ffynon Oer Windfarm has a community fund of £1,000 per MW installed
and the fund proposed for the Mynydd y Gwair windfarm proposal north
of Swansea also has a proposed fund of £1,000 per MW
Should a capital
sum, or part capital sum payable at the beginning of the project be
preferable for the funding schemes envisaged then a proportionate
sum would be discounted back from the annual fund. If the whole fund
was discounted back then a fund available at the beginning of the
windfarm operation would be £600,000.
This funding is
dependent on the windfarm being constructed within time to secure
the current government electricity sale price arrangements. The planned
timetable is for construction to start in 2008 and finish in 2009.
Should the project be constructed later, and fall outside the limits
then the fund would need to alter in line with the altered price arrangements.
The Government have not said by how much the funding will alter at
this stage, or the exact cut off date.
Although a voluntary
fund, the fund is being offered to be legally secured by the Council.
The commitment is over a long period and it will therefore be necessary
to include some protective measures to address certain risks beyond
the windfarm operators control. These would be established through
legal agreement, but the principle one is the political risk surrounding
government support mechanisms. Should the support mechanisms applicable
to the windfarm be removed or materially reduced then it may be necessary
to re-appraise the income of all stakeholders, including the community
fund. To avoid concern that commitments were being weakend it is proposed
that an independent arbitrator would decide on any adjustments proposed
by the windfarm operator in this situation. For the avoidance of doubt
should the scheme be larger or smaller than planned this would reflect
in the available community fund also.
It is suggested
that funding should be concentrated on communities that have the strongest
link with the windfarm. This link is more clearly evident in a visual
link. Maerdy windfarm has a discrete visual profile such that it is
not visible from most surrounding communities. A detailed analysis
of visibility is provided in the Landscape and Visual Chapter of the
Maerdy Windfarm ES. Figure 2.1 below shows the zone of theoretical
visibility of the windfarm.
The communities
with the strongest visual link are Treorchy in the Rhondda Fawr and
Maerdy in the Rhondda Fach; a weaker visual link exists with some
communities in the Cynon Valley, principally part of Cwmdare and Llwydcoed.
Figure 2.1 Zone
of Theoretical Visibility

Note: This ZTV should not be used for visual evaluation of the windfarm
– Reference should be made to the ZTV’s within the ES.
Visual influence
is not black and white and there are no clear cut off lines to be
drawn, but the above locations are the centres of visual influence.
It is likely that
with other windfarm proposals being made over time, eg the proposed
Hirwaun Windfarm, there will be closer and more relevant windfarms
to the Cynon Valley.
For these reasons
it is suggested that funding should concentrate significantly, if
not completely, on the communities of Maerdy and Treorchy in the Rhondda
Fach and Fawr. It is suggested that the windfarm would have approximately
equal influence and association with both valleys and as such funding
should be split equally between the two.
Influence of the
windfarm and needs of the community do not neatly end at the Maerdy
and Treorchy boundaries. However, trying to apply complicated dispensations
to other affected communities is thought to be a recipe for argument
and conflict. It is suggested that the best and most community engaging
way to address peripheral benefit outside Maerdy and Treorchy is to
allow the goodwill of the Maerdy and Treorchy communities to dictate.
It is suggested that each community has dispensation to apply funding
as THEY see fit, including neighbouring communities etc, through their
goodwill and sense of fairness. It is hoped this solution to geographical
discrimination will foster settlement of difficult issues in a spirit
of community engagement rather than division.
Therefore it is
the proposal for consultation that the community fund be split equally
between Maerdy and Treorchy. Comments are requested.
TAN8 planning
policy has guidance on the application of funding including possible
beneficiaries. Past windfarm schemes have funded educational grants,
environmental measures, etc..
The public consultation
conducted by the Developer has provided some ideas and direction on
local feeling about how funds should be applied. It is acknowledged
that the number of people who responded to the consultation is not
a statistical sample and ideas rather than conclusions should be drawn.
The Developer plans to conduct a further period of consultation in
parallel with the planning application and it is hoped this will provide
further guidance. It is also hoped that further ideas may arise from
community groups including the Council.
The Developer
wishes that while it facilitates development of the fund and its management
it should not decide on the application of the fund; that should be
decided by the local community. While the Developer specialises within
its industry in community engagement, they do not have the expertise
warranted to maximise community benefit locally. Further, while they
have three and a half years experience in the area, there is greater
knowledge about local needs held with others.
Lastly, it is
desirable to foster a sense of ownership of the community fund and
it is therefore for the community, not the Developer, to decide on
fund application.
The key questions
are the mechanism of funding and the control of that funding.
Some windfarm
benefit schemes are managed by the windfarm developer, however several
have an independent trust. TAN8 recommends that “benefits are
channelled through a regulated and properly constituted body or trust”
A trust provides independence from the windfarm developer or operator
and ensures local control. It also provides a tried and tested legal
mechanism for protecting the funding. It is therefore suggested that
two independent, properly constituted, community trusts be established
for the Maerdy and Treorchy Funds.
One comment coming
through the community consultation was the need for a clear and visible
connection between the windfarm and the fund. The Developer is therefore
keen that the funds are independently managed i.e. they are not managed
by another group. This way there is a direct link and identification
between the community fund and the windfarm.
Further, the Developer
is keenly aware, from the consultation done, how control of funding
within a community has the danger to be divisive. If control of funding
rests with a single group, this can cause resentment and political
division, no matter how good a job the controlling group may be making
of managing the fund. The Developer does not want any community fund
to be divisive, but to be constructive to community relationships.
The Developer
proposes that two democratic funds are established that have written
into their constitution the principal of one resident, one vote. Hereby
every resident of Treorchy or Maerdy would have equal say over what
happened to their fund. It is hoped that this would:
- avoid any group
control issues;
- create a real
sense of “ownership” of the fund amongst the community;
- create empowerment
amongst all members of the community, particularly the disadvantaged
and less involved in the community;
- put the decision
making in the hands of those who best know what the local needs
are.
The trust funds
would have a management board similar to most trusts, including upstanding
members of the community, accounting and legal advisors, political
representatives, etc. However, the critical difference would be that
the trust board did not have decision making powers over application
of the fund, only its management.
Running such a
democratic fund is practical for communities the limited size of Maerdy
and Treorchy with today’s communication facilities. Proposals
for funding would be invited and then publicised on a Community Fund
website, in libraries, by leaflet and hopefully in newspapers. Then
there would be an annual meeting, with the opportunity for residents
also to vote by post, or internet on which applications were successful.
It is suggested
that the funds are called the “Maerdy Wind Fund” and the
“Treorchy Wind Fund” to establish connection between the
source of the funding.
Recommendations
for membership of trust boards are invited.
TAN 8, above,
sets out the legal and planning issues regarding funds such as this.
Difficulty can occur in enshrining commitments in planning conditions.
The Developer therefore intends to enter into an appropriate legally
binding agreement that secures the commitments offered.
This report contains
information relevant to the development of a community fund from the
Maerdy Windfarm proposal.
It is argued that two community funds be developed, one for Maerdy
and one for Treorchy; and that these are democratic funds where each
resident of the community has a vote on how the funds are spent.
Total funding
of £50,000 per year, indexed at 1.5%, for the life of the windfarm
(circa 25 years), or alternatively a £600,000 capital sum at
the beginning of the windfarm is offered (or combination in between
these two alternatives); this total funding to be split equally between
the two funds.
These are sensitive
and difficult decisions, and the Developer welcomes comment on all
aspects of the suggestions outlined. The intention is that after consultation
a legally binding agreement would be entered into that the Council
can rely upon.